MPI-I-98-1-026
Improved approximation schemes for scheduling unrelated parallel machines
Jansen, Klaus and Porkolab, Lorant
November 1998, 14 pages.
.
Status: available - back from printing
We consider the problem of scheduling $n$ independent jobs on $m$ unrelated
parallel machines. Each job has to be processed by exactly one machine,
processing job $j$ on machine $i$ requires $p_{ij}$ time units, and the
objective is to minimize the makespan, i.e. the maximum job completion time.
We focus on the case when $m$ is fixed and develop a fully polynomial
approximation scheme whose running time depends only linearly on $n$. In the
second half of the paper we extend this result to a variant of the problem,
where processing job $j$ on machine $i$ also incurs a cost of $c_{ij}$, and
thus there are two optimization criteria: makespan and cost. We show that for
any fixed $m$, there is a fully polynomial approximation scheme that, given
values $T$ and $C$, computes for any fixed $\epsilon > 0$ a schedule in $O(n)$
time with makespan at most $(1+\epsilon)T$ and cost at most $(1 + \epsilon)C$,
if there exists a schedule of makespan $T$ and cost $C$.
-
- Attachement: MPI-I-98-1-026.ps (241 KBytes)
URL to this document: https://domino.mpi-inf.mpg.de/internet/reports.nsf/NumberView/1998-1-026
BibTeX
@TECHREPORT{JansenPorkolab98-1-026,
AUTHOR = {Jansen, Klaus and Porkolab, Lorant},
TITLE = {Improved approximation schemes for scheduling unrelated parallel machines},
TYPE = {Research Report},
INSTITUTION = {Max-Planck-Institut f{\"u}r Informatik},
ADDRESS = {Im Stadtwald, D-66123 Saarbr{\"u}cken, Germany},
NUMBER = {MPI-I-98-1-026},
MONTH = {November},
YEAR = {1998},
ISSN = {0946-011X},
}